Ongoing Commercial Build

TTB-2026-M4N5O6
Overall Progress
65%
Ongoing
Project Phases
Planning Completed
Dec 01, 2025 — Dec 20, 2025
Mobilization Completed
Jan 05, 2026 — Jan 25, 2026
Construction Active
Feb 01, 2026
Finishing Pending
Turnover Pending
Progress Updates
Apr 30, 2026
MEP Rough-In and Office Mezzanine
65% complete

Electrical and plumbing rough-in at 70% completion. Office mezzanine structural steel fabricated and installation underway.

Mar 20, 2026
Roofing and Exterior Walls
50% complete

Main roofing installation completed. Pre-cast exterior panels are being installed. MEP rough-in has begun on the ground floor.

Feb 15, 2026
Foundation and Structural Steel Completed
30% complete

Foundation works, footing, and ground floor structural steel erection have been completed. Ready for roofing installation.